Whirlwind Bike Earned Value Question

Whirlwind Bike Earned Value Question         
Planned cost (BCWS) week 6  194,000 Planned Duration  12 periods
Work Package Dur BAC %complete EV Actual Cost
Start-up and mobilisation 1            5,000 100%         5,000                  5,000
Design frame 2          60,000 95%      57,000               57,000
Design wheels 1          10,000 100%      10,000               12,000
Design the ancillaries 1          10,000 100%      10,000               15,000
Build the frame 4          60,000 0%                –    
Build the wheels 2          20,000 70%      14,000               14,000
Build the ancillaries 1          20,000 90%      18,000               17,000
Integrate the bike 2          40,000 0%                –    
Test the bike 2          20,000 0%                –    
Launch the bike 1            5,000 0%                –    
Project Management  12          48,000 50%      24,000               22,000
Total         298,000      138,000             142,000
           
CPI = EV / AC 0.97        
SPI = EV / PC                 0.71        
SV= EV – PC –          56,000        
CV = EV – AC –            4,000        
           
Actual completion = planned duration / SPI               16.87        
           
EAC = BAC/ CPI          306,638        
Avatar for Paul Naybour

Paul Naybour

Paul Naybour is a seasoned project management consultant with over 15 years of experience in the industry. As the co-founder and managing director of Parallel, Paul has been instrumental in shaping the company's vision and delivering exceptional project management training and consultancy services. With a robust background in power generation and extensive senior-level experience, Paul specializes in the development and implementation of change programs, risk management, earned value management, and bespoke project management training.

4 thoughts on “Whirlwind Bike Earned Value Question”

  1. Adelle Well spotted I think its a rounding error on CPI. CPI is 0.971830985915493 so EAC is 306.6376811594203….excel……

  2. Hi – I’m a bit stuck and wonder if anyone can help please.

    If the BAC is 298,000 and the CPI is 0.97, shouldn’t that give a EAC of 307,261? Not 306,638

  3. Hi Paul,

    Fully understand how you arrived at your cals but the question then asks to draw the cost curves for EV and AC, How do you do this?

    Many thanks

  4. @epicday all you can do is plot the three points you have calculated and join with straght lines. So you have zero for all three at the start, AP and EV at week 6 and then the EAC and forcast actual completion.

Leave a Comment

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Upcoming Courses

Scroll to Top