Mock Exam Paper A – Question 7 – EV

Hi Paul

I’ve attempted question 7 from Mock Exam Paper A from your book (Q: Consider the chart below and make some calculations and comments). Could I ask you to have a look and see if you think the calculations are correct and whether the comments give enough info for the full 50 marks, or if I? should be adding a bit more?

Question Details :

AC = 480,000

PC = 390,000

EV = 320,000

OD = 20m

BAC = 1,000,000

Comment on SV (or SPI), CV (or CPI), Estimated Cost + estimated time at completion.

 

My Calculations :

CV = EV – AC = 320,000 – 480,000 = -160,000

SV = EV – PC = 320,000 – 390,000 = -70,000

CPI = Ev/AC = 320,000 / 480,000 = 0.66

SPI = EV / PC = 320,000 / 390,000 = 0.82

EAC = BAC/CPI = 1,000,000 / 0.66 = £1.52M

ETC = OD/SPI = 20 / 0.821 = 24.36m

 

From the calculations, the following can be observed :

1. CV is negative which indicates that the project has spent £160k of actual money more than the value of work received.

2. SV is negative which indicates that the project has achieved £70K less work than was actually expected at month 10. In addition, the project has spent £90k of actual money more than was planned at month 10.

3. The estimate at completion places the finished costs at £1.52M which is 50% increase above the original estimate, if the current rate of work and spend is maintained.

4. The estimated time of completion is 24.36 months which is a 20% increase over the original estimate.

5. Overall the project has been under performing since month 3, consistantly received less value than planned and that which has been received has cost more than estimated. Looking at the graph, the estimated costs are increasing diverging from the planned costs which tend to indicate the situation will continue to get worse. There are a variety of reasons for the situation arising, possibly caused by bad estimates, ineffectual resouces or lack of direction.

 

Any comments you have would be much appreciated,

 

Many Thanks

Paul

 

Paul

Avatar for Paul Naybour

Paul Naybour

Paul Naybour is a seasoned project management consultant with over 15 years of experience in the industry. As the co-founder and managing director of Parallel, Paul has been instrumental in shaping the company's vision and delivering exceptional project management training and consultancy services. With a robust background in power generation and extensive senior-level experience, Paul specializes in the development and implementation of change programs, risk management, earned value management, and bespoke project management training.

Upcoming Courses

Discover more about professional project management certification
and how it enhances the career prospects of individuals and the project delivery capabilities of organisations.

Scroll to Top