Describe The Role Of The Programme Manager, Make Five Points

The Programme Manager has to plan and schedule the projects to deliver the benefits as early as possible, for example if a the programme was to introduce a new production line, in a new building to include a new machine, and a new crane to handle the products for the machine.

 

The programme manager would perhaps organise the projects 1, a new access road to the site of the new building(enabling plant and labour to get to the next project), 2, the new building(cover and a base for the new machinery and crane), 3, the overhead crane and training, into the building(installed before the machinery and workers trained in its use, to aid in the handling of the new machinery installation, saving costs on additional cranage), 4, the new machinery.

 

The Programme Manager needs to be able to prioritise resources across projects; for example if the new production line programme above has progressed better than expected and is ready for the power cable to be installed, but the in electricians are working on the next phase of the programme, the programme manager may want to delay that project and prioritise the resources in this instance the electricians and the cable to finish the new production line, and enable production (business as usual) to start, realising those benefits for the business early.

 

 The programme manager will support and motivate the project teams, for example a project manager may be struggling to resolve conflicting interests between the project and business as usual, the programme manager may advise on a path forward, or even assist in negotiations with the conflicting parties, and help bring about a satisfactory outcome.

If a project is struggling the programme manager might agree to divert extra resources to bring the project back on course.

 

The programme manager should make sure that Risks and lessons learnt are communicated across all the projects in the programme, the projects should be working to the same assurance criteria, it is important that all projects in the programme sing from the same hymn sheet, for example all engineers working on site on any of the projects will have the same site specific induction, although some may have additional inductions to suit their area of work.

Perhaps a specific contractor is constantly late with deliveries, this information should be passed onto other projects in the programme, perhaps it will be decided that the preferred supplier is dropped, for the other projects.

Perhaps a very hot summer has caused heat stress problems at height, this will need to be conveyed to the other projects so precautions can be put in place and monitored.

 

The Programme Manager should communicate with the project teams and the business, for example if a large delivery is expected at a certain time and date, the business will need to be informed of the plans, it may be that the business has an extremely urgent job that has to be completed at just this moment in time and to delay it, could invoke penalty clauses that would cost a substantial figure,  it may be better to delay or bring forward the timing of the projects large delivery to avoid conflict of interest. The program manager would convey this information to the project team.

Avatar for Paul Naybour

Paul Naybour

Paul Naybour is a seasoned project management consultant with over 15 years of experience in the industry. As the co-founder and managing director of Parallel, Paul has been instrumental in shaping the company's vision and delivering exceptional project management training and consultancy services. With a robust background in power generation and extensive senior-level experience, Paul specializes in the development and implementation of change programs, risk management, earned value management, and bespoke project management training.

1 thought on “Describe The Role Of The Programme Manager, Make Five Points”

  1. Dave, Your words indicate a programme manager being the manager of several project to achieve a strategic objective, but the examples you give are more tactical, and could refer to a project manager or even a planner. Remember in the APMP a programme is not the schedule but a strategic programme. You description would fit a senior project manager, which in many organisations might be called a programme manager. I would talk more about

    1) selecting which project should form part of the programme
    2) Defining the benefits across several projects and how they combine to give one overall benefit.
    3) Interdependence between different parts of the programme.
    4) Managing common risk that exist across the projects in the programme and may threaten the benefits
    5) Communicating with senior stakeholders the vision and mission of the project (bullS**** but I am sure I could spin it out)

    Most importantly htey are not the jobs a project or senior project manager would be expected to do, unless someone disagrees with me…….

Leave a Comment

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Upcoming Courses

Discover more about professional project management certification
and how it enhances the career prospects of individuals and the project delivery capabilities of organisations.

Scroll to Top