Feedback Required – Governance Example Questions
I am taking my APMP exam in 3 weeks time. Have started exam papers and looking for feedback please. This […]
I am taking my APMP exam in 3 weeks time. Have started exam papers and looking for feedback please. This […]
1) Programmes are strategic in nature Programmes are usually part of a larger vision of an organisation and will initiate,
1) Projects are unique Projects are unique and have not been done/executed in this specific way before. Business as usual
List 5 characteristics of Project and describe how each is different from BAU 1. Limited duration Projects are temporary endeavours
Answer: a) Businesscase provides justification for undertaking a project or programme, evaluating thebenefit, cost and risk of alternative option,
Given the predominance of projects in almost all large organisations, their value to an organisation is understood and appreciated but
This infographic highlights the key ways a project manager can use a Gantt chart to keep projects on track. Infographic
Explain what is meant by the term Project Scope (10 Marks):- Project scope is all the products produced, and all
Explain what is meant by the term Project Governance (10 Marks):- Project Governance is the framework by which an organisation’s
Describe the main key phases of a life cycle and the activities and outputs of each The main key phases