APM PMQ (BoK7) Earned Value – Podcast Transcript

Introduction

Welcome to a parallel project training APM project management qualification (APM PMQ) podcast based on the APM body of knowledge seventh edition. You should be using this in conjunction with our elearning podcasts, and potentially a tutor led course. For more information, please visit www.parallelprojecttraining.com

Paul 

Hello, welcome to this Parallel Project Training podcast. Today we’re looking at our favourite topic – earned value.

John 

Yes, hello, Paul – love earned value.

Paul 

This is quite a big change in earned value for this syllabus. But anyway, let’s go through the assessment criteria. Explain why project managers should use earned value, interpret and value data including variances and performance indices, expand the benefits of interpreting and value and expand the role of contingency planning and projects. So we’re not doing any, we don’t have to do the sums of calculating Earned Value anymore.

John 

No, no. I mean, basically there is this new form of torture called interpret interpret. Yeah, so they give you a diagram and go or give you some numbers and you have to figure out what’s going on. Yeah. You have to sort of synthesise, and you have to you have to look at those numbers and kind of read into them what could be going wrong on a particular project?

Paul 

What you do quite often in a project environment Anyway, you go to a progress meeting. And someone hands a report to you as you go in the door.

John 

Yeah, but I mean, if you got it if you’ve got a CPI of point eight, yes. I mean, interpret that. What does that mean? Well, that means that we’re overspending on costs, we’re really efficient. But that could be the result of billions of different reasons, you know, so I’m not, you know, we can go through few of them. But there might be many reasons why that’s happening. Yeah. So there’s not a definitive kind of List of these. But the essence of it is, is that you’re working out some sort of, if you figure out your own value, right, that’s what

Paul 

Explain why a project manager should use earned value. Let’s do that first

John 

Okay, well, the principle is that you can’t tell how well your project is doing simply by comparing what you’ve spent with what you thought you were going to spend. So you need another measure. So you need a third axis on your graph. So the curve on your graph, which is progress, progress is calculated. So the third the third act, the third curve is earned value. And that’s calculated by taking the budget completion, multiply it by the percentage complete. Yes. So if you’ve got a war that’s worth three grand, and you’re two thirds of the way through, you’ve got 2000 pounds worth of earned value, putting it very crudely. So you plot those figures, you plot how much you spent, how much Earned Value you’ve got, and you compare the actual span of the plan costs with your own value, and that gives you indices and indexes and variances. It works on the basis that the only really good answer is your own budget, and you’ve delivered stuff according to the budget. So if there are no variances on earned value or actual costs, so that’s the principle. So the consequence of that is that any deviation is bad. Yeah, even if it’s positive,

yes.

Paul 

Is that we’re not necessarily good.

John 

It’s difference is a deviation. Yes,

so that a deviation positive or negative is not in itself a good thing. However, I thought would be finishing early is probably better than finishing it. No, no, I don’t know. I don’t agree with you. I don’t I have a real problem. I

Paul 

remember the slowdown that

John 

yes, if you will. Okay, so let’s, let’s think about that. Then I’ve got two people on site. One’s building the roof and one’s building the walls. I mean, how old? Yeah, all right. I don’t want the bridge deck delivered before the piers for the whole project, but I don’t want the top of the rocket finished before the bottom of the rocket, because I don’t know where to put it.

Paul 

Yeah. Okay. So at

John 

each level, and also don’t forget, you’re spending money early. So there’s this rush to burn money. Yeah. Where’s the actual fact it smooths out your

Paul 

cash flow? I mean, generally, people will say that if it’s if the whole

John 

planning the whole planning cycle is predicated on starting as soon as you can, yes. Which is not always a great idea.

Paul 

So let’s go back a little bit and talk about these measures that we do. So there’s basically two sets of measures of variances honour. So when a variance what we do is look at what our earned value is, we compare it to what we should have spent our actual cost. And what we plan to spend our planned planned cost as planned costs, what we should have spent actual costs what was actually spend, so we end up with cost variance, and we end up with a schedule variance, and those should be zero. So basically, we’ve spent what we expected and we’ve delivered what we expected and then the A set of measures our performance indices, and now we do exactly the same. But we compare earned value to the actual cost and earned value to the planned cost, but we do as a ratio. So they were looking for the measures to be one to one means one plan. greater than one means were ahead of plan or delivering more efficiently, less than one means we’re behind plan or delivering less efficient. So we were just talking about is, ideally you want to be on plan, in terms of delivery. And in terms of

John 

progress. I mean, I think the other thing is that, you know, you see people coming up, I’ve got a CPI of naught point seven or 1.7. Okay, and they’re going “really clever aren’t I really good”? Quick? So 170% efficient? Yeah, you’re gonna ask a few questions. Yeah, Don’t forget you see if you’re if you fit that means you got to finish early. Yes. And under budget? Yes. Well, the business of the time, no snow, the business has set aside all that money to pay for your project. Okay. So they have no, they have to spend it elsewhere. Yes, yes. Yes. So your business has held back all that money in New York coming in? Why?

Paul 

Jesus nicely under forecasts? Yeah. So from those performance indices, we can then do a forecast. And that forecast sort of projects, our current cost performance and current scheduled performance. And so we can turn around to the business and say, I’m currently a little bit ahead. And I think that I might finish this project a little bit ahead, or I’m currently slightly over budget. forecasts.

John 

Nothing wrong with being early a bit under budget, you know, no one’s gonna moan about that. Yeah, or being a bit late. But over budget, it’s not the end of the world. But it’s too late to realise at the end of it,

Paul 

so that’s right. That’s a sackable offence

John 

to be one to be one month away from the end of them. And then finally, your budget got to be Yeah, it was. Yeah, yeah. That’s, that’s 90% of the way through realises another 90%. ago.

Paul 

Yeah, that’s, that’s all for life. So. So that’s the fork. So basically, from these measures, we can we can do some forecasting,

John 

but when you interpret the data, they’re either going to give you a graph, I think, I don’t know. I mean, whatever data on it. Yeah, it depends on how exactly. SPI CPI No, you know, given those No, you don’t do the calculation says

Paul 

SPI equals and a CPI.

John 

So also quite quite what the answer the question is, oh, God only knows,

Paul 

because I think you just play it absolutely straight back. So in my SPI is 1.1. Yeah, that means my head of plan, my CPI is naught point eight. That means I’m overspending for what I’ve delivered.

John 

That’s not the question they ask you, though. That’s it. They don’t ask you that. They say you’ve got a CPI of naught point eight. Explain what might be going wrong on the project. I’m running late here, though. But that’s so why

Paul 

I don’t have enough data to answer that question. So yes, that’d be running late for a number of reasons.

John 

Yeah. Well, but that’s what it says in the sample paper.

Paul 

Okay, well,

John 

okay. So again, some of the people that are listed exactly the people that listen to this need to understand how to answer that. Okay, well,

Paul 

I’d say, I could be running late for a number of reasons scope, because

John 

I might not be able to get resources this way. So may have, it’s a comparison between the CPI and SPI as well. So you look at both of them together. Okay. Because just saying I’m late, because you can’t really tell much from that and help with that. Actually, yeah. Because there isn’t, there are things that you can deduce from the relationship between the CPI and the CPI. So if you’re, if you’re spending too much, but you’re late, you’re probably inefficient, yes. Which means that the people are working odd and spending a lot of money. They’re not getting anywhere. Yes. So you might find that there’s lot of rework or incoming materials, not very good. scope is poorly controlled. But conversely, if you’re early, so I were what was the last one over budget and late, you can be under budget and early. Right. So what that means is really that you’re, you’re very efficient, you could probably afford to slow down a little bit if you needed to. Or, you know, you might want to re estimate the project, because you’re kind of you’re kind of doing too well,

Paul 

on the most common one I’ve seen is you really liked. We’re not spending enough.

John 

Yes, that’s right.

Paul 

So the team you have is been efficient, because they’re delivering more value than cashing in. But you just haven’t got enough result.

John 

enough resources. So there are

Paul 

some, it’s, you could say this is indicative of that sort of situation, you know, yeah. And I suspect we’ll do it.

John 

We’ll do in the course as well there. Yeah. I mean, if you if you read if you read our material, there are some parts. Project one, two and four. Yeah, there’s there’s four examples. There’s, there’s four main examples of the interpretation. But yeah, when you say the question is, it’s a bit you know, without the data, it’s very difficult to be definitive. So you have to realise or more generic answers I can see that will develop over time. Well, yeah, once once the examiners work out what he

Paul 

earned value and values measure those three things, the planned cost, that what we’ve actually spent and our progress in terms of earned value then comparing them and you can compare them as variances differences or distractions from they can forecast what your end is going to be. And you can do some sort of arm waving indicative interpretation or waving of mostly around how efficient your resources you know, are you put in is, is the I put enough money in to get the progress you want or is more money going in the progress you’ve achieved? Brilliant. Excellent. Okay, John.

We hope you enjoyed this podcast and found it informative. To find out about our training courses elearning or tutor led course please go to www.parallelprojecttraining.com

Avatar for MS

MS

Michelle Symonds is a digital marketing consultant and founder of Ditto Digital. She has worked with Parallel Project Training developing and implementing their SEO and content strategy since the business was first founded.

Leave a Comment

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Upcoming Courses

Discover more about professional project management certification
and how it enhances the career prospects of individuals and the project delivery capabilities of organisations.

Scroll to Top